2019-10-28: "Three - two - one - Go!": First flight - successful debut launch of the Einstein-Elevator.
2019-07-16: Space for 1.000 kg payload: The first version of the experiment carrier is ready to fly.
2019-03-07: The first drop of the gondola: The gondola is dropped from the upper starting position and braked with the help of the short-circuited drive.
2018-11-22: It's time: The gondola is inserted through an opening in the ceiling into the Einstein-Elevator.
2018-11-10: A night out with science: Visit us at the HITec building and get an idea of what we're doing here.
2018-10-24: Ready for the gondola: The guide rails for gondola guidance are finaly mounted with an accuracy of 0.1 mm at 33.000 mm.
2018-07-02: Welcome to Germany: The gondola arrives in Germany at its last stop for a long-time vacuum test before mounting into the Einstein-Elevator.
2017-10-05: Lowering one of the two carts by crane to park position at the bottom of the Einstein-Elevator
2017-05-22: The work platform has been installed: now the cabling starts and additional devices will be installed.
2017-02-21: The steel framework is finished: the parts of the outer and inner tower are mounted and aligned.
2017-02-14: Inner and outer steel frame reach the final height: Now you can imagine what it will look like.
2016-12-20: Construction of the Einstein-Elevator starts: First parts of the steel frame are mounted.
2016-11-17: The construction work continues: Ready to install the inner steelwork e.g. stairways, levels and the Einstein-Elevator itself.
2016-10-14: Externally finished: The facade of the tower is mounted and the scaffold is now being dismantled.
2016-10-05: The foundation for minimal residual acceleration: the individual ring foundations for the two intertwining towers.
2016-09-26: Visualization of the concept: 3D-printed model of the Einstein-Elevator with moveable gondola.
2016-09-22: 3D-printed model of HITec and the Einstein-Elevator together with their surrounding buildings (Part 2).
2016-09-19: 3D-printed model of HITec and the Einstein-Elevator together with their surrounding buildings (Part 1).
2016-08-29: Picture from outer space: HITec and the foundation of the Einstein-Elevator photographed by a satellite in 2015.